  • Construction of Kertajati Airport reaches 64.2%

    Construction of Kertajati Airport reaches 64.2%

    Kertajati Airports construction project in Majalengka, West Java, comprising access, drainage, interchange ramp, and parking lots has reached 64.2% on Jan 29, PT. Bandarudara Internasional Jawa Barat Director Virda Dimas Ekaputra stated.

    The construction of the Kertajati Airport comprises three working packages, Ekaputra noted.

    Package 2 encompasses the construction of the main passenger terminal building in cooperation with PT. Wijaya Karya and PT. PP, with a contract value of Rp1.39 trillion.

    Meanwhile, Package 3 comprises the construction of facilities for supporting operations, such as a cargo terminal and regional electrical connection by PT. Waskita, with a contract value of Rp416 billion.

    “The work on Package 2 has reached 19.94%, while that on Package 3 has reached 35%,” Ekaputra stated.

    Hence, he noted that the overall progress of the Kertajati airports construction project has reached 30% on February 5, 2017.

    Ekaputra pointed out that the cost for Phase 1 reaches Rp2.1 trillion of the total development investment of Rp4.5 trillion.

    He expressed optimism that the infrastructure work would be completed on July 3, 2017; the building to support operations on August 8, 2017; and the terminal building on December 6, 2017; while the initial operations will begin in January 2018 and full operations in March 2018.

  • Kertajati airport project to cost Rp3.7 trillion

    Kertajati airport project to cost Rp3.7 trillion

    The Kertajati airport project in West Java will cost around Rp3.7 trillion, to be paid by the central governmernt West Java Governor Ahmad Heryawan said.

    The central government through the transport ministry will finance the construction of the international airport in the regency of Majalengka, the governor said here on Monday.

    President Joko Widodo announced the decision on the project financing during his visit to Majalengka on Sunday.

    The governor said construction of the runway and the monitoring tower will cost around Rp1.6 trillion and the terminal and other facilities will cost around Rp2.1 trillion.

    The West Java administration is to pay only for the 1,800 hectare land clearing, the governor said, adding land clearing has been 1,000 hectares completed.